During the meeting, several resolutions and their specifics were discussed, particularly focusing on the development of a multi-use stadium and related financial arrangements. Here are the key points from those discussions:

  1. Resolution for Change Order:
    • Name: Change Order Number Two to the CM Contract with EMJ Construction LLC for the South Broad District Ballpark Project.
    • Dollar Amount: Early release package number two amounting to $29,437 with an additional $1 million contingency, revising the total amount to $51,655,078. However, this item was requested to be withdrawn for timing alignment with financing documents and bond issuance.
  2. Memorandum of Understanding (MOU) Regarding Stadium Financing and Development:
    • Name: Memorandum of Understanding Relating to the Financing and Development of a Multi-use Stadium.
    • Discussed detailed financing plans involving city, county, and sports authority contributions towards the stadium's development, totaling an estimated cost of $115 million. This includes $80 million from bonds issued by the Sports Authority, supplemented by various sources including sales tax revenues, team rent payments, and tax increment revenues.
  3. Resolution for Promoting Inclusion of Disadvantaged Business Enterprises:
    • Name: Resolution Regarding Utilizing the City of Chattanooga's Staff to Assist with Promoting the Inclusion of Disadvantaged Business Enterprises in Connection with the Construction and Operation of the Stadium.
    • A resolution to use city staff for promoting diverse participation in the stadium's construction and operation phases, ensuring opportunities for minority and women-owned businesses as well as service-disabled veteran-owned businesses.